JUBA, South Sudan – The Greater Pioneer Operating Company (GPOC) has fenced an oil waste pond at Unity Oil Field more than two months after a woman fell into it, following an earlier commitment to secure the facility.
In a statement on Wednesday, GPOC said its Vice President, Eng. Biem Andrew Thon, inspected the fenced pond during a visit to the oil field. The company described the fencing as a “critical measure designed to prevent hazards to local residents and livestock.”
GPOC had promised to immediately fence the open drainage pit after a government inspection on September 15, two days after the incident.
A woman identified as Kasare Nyier Gatluak fell into the pit on September 13. She was rescued and taken to Bentiu State Hospital before being transferred to Gudele Hospital in Juba for further medical treatment.
Following the incident, a Unity State lawmaker gave GPOC 30 days to fence and clearly mark all oil waste ponds, pits and other hazardous sites across its operations in the state.
He also demanded a verified completion report, a joint independent investigation into the incident and a permanent community safety programme, including warning signs in local languages and a mechanism for reporting hazards.
GPOC’s November 25 statement did not say when the fencing was completed or whether other hazardous sites had been secured. It also gave no update on the proposed investigation or the completion report.
During the visit, Thon also inspected the newly constructed Manga Port, developed jointly by GPOC and the United Nations to facilitate the transportation of heavy equipment into the region.